Cabinet installation checklist

43 checks for the whole install, from the delivery truck to handover. For installers, contractors and anyone checking the work.

By the Punchlee team, built by a contractor for contractors. Updated September 30, 2026.

Most cabinet problems that show up at the end of a job were decided in the first hour: a missed damaged box, a level line taken from the low point of the floor, or a wall cabinet screwed into drywall. This checklist follows the order of a real install day.

The rule that saves the most time: the countertop is only as flat as your base cabinets. If the fabricator has to shim a countertop, the problem started with the bases.

Before install day

Base cabinets

Wall cabinets

Tall cabinets and panels

Fillers, scribes and trim

Doors, drawers and hardware

Before the countertop template

Handover

Turning what fails into a punch list

Every item that does not pass goes on the punch list with a photo and a name: which cabinet, what is wrong, who fixes it. For cabinet work that is usually the installer, but damaged boxes go to the supplier and gaps at the wall may need the painter or drywall crew. Write it so the right person can fix it without calling you; here is how.

Punchlee: choosing who fixes an item, with the cabinet installer listed
Assign each item to the right trade, so the cabinet installer only sees cabinet items.